HAFB - Emergency Repair, Wall Damage, Building 1173

Existing west end of Building 1173 was damaged by the wind due to structural issues. White Sands Construction plans on removing existing west side of building to an elevation of 25’ (existing beam) to include galvanized metal sheeting (approx. 1200 sq. ft.), existing vinyl insulation,  c-purlins, and existing 16’ tall x 12’ wide overhead door/motor.

White Sands Construction will either provide plastic to protect interior of building or if operable, will bring down existing overhead door.

White Sands Construction will install three new 8”x8” square columns, anchored into concrete and welded to the existing beam at an elevation of approx. 25’. 6- Rows of new 8” c-channel (welded in place, including new channel at existing beam for sheet attaching) will be installed horizontally between the columns and above the new overhead door. New galvanized 24 gauge sheeting will be installed on the new structural framing along with new R-19 vinyl faced insulation. A new 16’ tall x 12’ wide overhead door and motor will be installed. The new door will be painted coco brown. All electrical accommodations including removal, re-connect, re-route, and new will be taken care of to properly accommodate new structural framing and overhead door.

Completion Date: 02/15/2011

Owner: Holloman Air Force Base

Architect: Design/Build

Location: HAFB, NM

WSCI Staff

Catlin Curry

Phone: 575-437-7816