Alto Otero County Electric

  • Alto Otero County Electric Co-Op - Misc. Work
    • Main Office:
    • South Door: Existing Storefront Door
    • Remove & Replace Storefront Door, Sidelight and Hardware
    • Clear Anodized Finish 4-6 Week Lead Time
    • West Door: Existing Hollow Metal Door and Frame
      • Remove & Replace Hollow Metal Door (no door lite in new), Frame, and Hardware
      • Existing door swings LHR - New door will swing RHR
      • Prep & Paint New Frame and New HM Door
    • Seal Galv. Sheet Trim/Concrete Sidewalk:
      • North (71’)
      • West (31’)
      • South (71’)
    • Lineman Shop:
    • West Door:
    • Remove & Replace Threshold Only
    • North Door: Existing Hollow Metal Door and Frame
    • Remove & Replace Door and Hardware (Frame to Remain)
    • Prep & Paint Existing Frame and New HM Door
    • Staking Office:
      • West Door: Existing Hollow Metal Door and Frame
    • Remove & Replace Door and Hardware (Frame to Remain)
    • Prep & Paint Existing Frame and New HM Door
      • East Door: Existing Store Front Door
      • Replace Panic Hardware Only - Clear Anodized Finish