Close
Skip to Content
High Contrast
Increase Text Size
Clear All
575-437-7816
575-437-7816
Home
About
Awards
Community Outreach
Our Team
Chevy Teague
Catlin Curry
Zeke Greer
David Malett
David Wootten
Debbie Lucero
Donald Yee
Ethan Schulz
Eugene Varbel
John Ballin
John Henderson
Joyce Tilbury
Kimber Parsons
Levi Williamson
Marc Davis
McChristie Curry
Mike Ford
Mike Watters
Norman Drews
Raul Ruiz
Ray Fletcher
Robert Amos
Steve Malett
Construction Services
Commercial Construction
Construction Management
Foundation Repair
Private Contractor
Testimonials
Reviews
Contact Us
575-437-7816
Top
Projects
Alto Otero County El ...
Project Info
Alto Otero County Electric
Alto Otero County Electric Co-Op - Misc. Work
Main Office:
South Door: Existing Storefront Door
Remove & Replace Storefront Door, Sidelight and Hardware
Clear Anodized Finish 4-6 Week Lead Time
West Door: Existing Hollow Metal Door and Frame
Remove & Replace Hollow Metal Door (no door lite in new), Frame, and Hardware
Existing door swings LHR - New door will swing RHR
Prep & Paint New Frame and New HM Door
Seal Galv. Sheet Trim/Concrete Sidewalk:
North (71’)
West (31’)
South (71’)
Lineman Shop:
West Door:
Remove & Replace Threshold Only
North Door: Existing Hollow Metal Door and Frame
Remove & Replace Door and Hardware (Frame to Remain)
Prep & Paint Existing Frame and New HM Door
Staking Office:
West Door: Existing Hollow Metal Door and Frame
Remove & Replace Door and Hardware (Frame to Remain)
Prep & Paint Existing Frame and New HM Door
East Door: Existing Store Front Door
Replace Panic Hardware Only - Clear Anodized Finish